I am explaining, the unique condition for CSIQ, accounting for modules which are delivered to projects but are not recognized as shipments until revenue comes in. What one should look for in the company like CSIQ is the behavior of the project assets line. From Q3 to Q4 that line increased by $88M. How many MW of modules have been hiding under this figure, until asset will be sold like in project complete- scenario? it could be easily 50MW or more just for single Q. If you think of this number of $400M and simply add 20% this is locked revenue, which has not been recognized to date.Keep in mind CSIQ gave pretty weak guidance in Q1 compared to Q4...
Odyd, I guess we just have a different view of the % of completion billing timelines. First, the 1-month delay for shipping I apply to all US shipments, so modules for projects are no different. In regards to your example, the project should be 100% finished and commissioned by September if started in February/March. But with % of completion, I would expect either monthly invoicing, or 30%/60%/90%/100% milestones or something like that. And since supplying the modules is one of the first things on the list, it should probably get billed out first.Example:
So say there is a US project CSIQ ships for installation in March. It takes 21 to 30 days on sea to get to the US port.
The delivery I see in February shows 50MW to the US.
If this was TSL I would expect this 50MW to be part of Q1 report. In CSIQ case this delivery may not be recognized until September, when partial or % of project completion is recognized as revenue. This is my point.
Sorry, my mistake...the external "billing" on % of compl only really happens on pure EPC work. But shouldn't the modules therefore be able to be fully recognized as revenue when they show up at the jobsite each month, with the backend % recognition being more based on installation and start-up costs? Or do they see things differently in the accounting world?But with % of completion, I would expect either monthly invoicing, or 30%/60%/90%/100% milestones or something like that. And since supplying the modules is one of the first things on the list, it should probably get billed out first.
But the more I think about it, there may be a month or 2 additional delay in the billing turnaround, which may or may not roll into next quarter's numbers.
Supplying modules is probably middle of the project work. My point was to highlight that CSIQ shipment guidance is no longer a sole indicator if company is successful or not, because of the project work and should be associated with project asset levels and revenue recognition from it, quarterly. Export data would be an essential confirmation to cover this gap. My example nano was actually project completed method, therefore delivering in January, has no relevance when modules were delivered, since the whole project is being recognized when whole project is completed.But shouldn't the modules therefore be able to be fully recognized as revenue when they show up at the jobsite each month
In the % of recognition the good news is that future owner carries financial responsibility for milestones payment which creates better cash flow condition.
Thanks...this is indeed very positive for CSIQ.At any rate it is a benefit without doubt, since more liquidity and less leverage is present.
Forum Software: Burning Board®, developed by WoltLab® GmbH
